Guide: phase 1, Initiate project

Both teams start. You set up the plan, the scope and the controls, and you close the phase at the Project initiated gate.

This page applies to the Initiate project stage.

Project manager guide

Agree what the project delivers, who does it and how it is governed. The Project initiated gate has 14 checklist items.

  1. State the scope.
    • Do now: Open Scope. List the benefits, the processes in scope, the exclusions and the acceptance criteria. Get the scope signed off.
    • Why: Written exclusions and acceptance criteria prevent most disputes in later phases.
    • The app checks: The gate checklist asks for a signed scope and for explicit exclusions and acceptance criteria.
    • Next: Build the plan.
  2. Build the plan and baselines.
    • Do now: Open Plan. Add the milestones and gate dates, record assumptions and dependencies with owners, then save the baselines.
    • Why: A baseline is the copy you measure every later change against.
    • The app checks: A baseline needs a recommendation from a project manager and then the decision of the steering group chair.
    • Next: Set up the organisation.
  3. Set up the organisation.
    • Do now: Open Organisation. Add the people, link each to a role and fill the responsibility matrix. Name the expert users and focus groups.
    • Why: Each activity needs exactly one accountable person, and the steering group needs confirmed members.
    • The app checks: The steering group is made of people with a confirmed steering group role. The page warns when nobody holds one.
    • Next: Start the registers.
  4. Start the risk and issue registers.
    • Do now: Open the risk register and the issue log. Enter the first risks with an owner, a probability and an impact.
    • Why: The gate expects both registers to be started. Review them at every steering meeting.
    • The app checks: To accept a risk you must write a trigger and a fallback. A closed issue needs a resolution.
    • Next: Agree who hears what.
  5. Agree communication and hold the first steering meeting.
    • Do now: Fill the communication plan and the stakeholder list. Plan the first steering meeting and record its decisions and actions.
    • Why: The gate asks for a communication plan and for a steering group that has met.
    • The app checks: The completeness check shows groups that nobody talks to. A meeting record can serve as evidence.
    • Next: Prepare the environments.
  6. Get the environments and access ready.
    • Do now: Open Environments. Register each environment with its purpose, owner and IFS version. Check that the team can sign in.
    • Why: The team cannot build anything without working environments.
    • The app checks: The app reads IFS data only. It never changes IFS Cloud.
    • Next: Work the gate checklist.
  7. Close the gate.
    • Do now: Open Gates and the Project initiated gate. Give each item an owner and link its evidence. Then request the decision.
    • Why: The steering group decides, and only then does phase 2 start.
    • The app checks: You can ask for the decision only when no item is untouched. A project manager recommends and the steering group chair decides.
    • Next: Continue with the guide for the Confirm prototype stage.