Change requests
Use a change request when scope, date, budget or a modification must change. No work starts before approval.
This page applies to every stage.
IDK templates: IDK-07
Page in the app: /p/{projectId}/r/change_request
Change control
The four baselines are schedule, cost, solution scope and project scope.
- Raise. Anyone on the team fills in the form.
- Assess. Both project managers check the effect on all four baselines.
- Decide. The project managers decide small changes. The steering group decides changes to a baseline, scope, schedule or budget.
- New baseline. An approved change makes a new baseline version.
- Implement. Work starts and the request is marked implemented.
How to do it
- Describe. State the need, the options and the cost of doing nothing.
- Rate the impact. Go through the impact areas. Say "none" where nothing changes.
- Submit. Send it for approval. The rules decide who must approve.
Good to know
- A draft or submitted request can be withdrawn.
- A deferred request can return to draft.