Change requests

Use a change request when scope, date, budget or a modification must change. No work starts before approval.

This page applies to every stage.

IDK templates: IDK-07

Page in the app: /p/{projectId}/r/change_request

Change control

The four baselines are schedule, cost, solution scope and project scope.

  1. Raise. Anyone on the team fills in the form.
  2. Assess. Both project managers check the effect on all four baselines.
  3. Decide. The project managers decide small changes. The steering group decides changes to a baseline, scope, schedule or budget.
  4. New baseline. An approved change makes a new baseline version.
  5. Implement. Work starts and the request is marked implemented.

How to do it

  1. Describe. State the need, the options and the cost of doing nothing.
  2. Rate the impact. Go through the impact areas. Say "none" where nothing changes.
  3. Submit. Send it for approval. The rules decide who must approve.

Good to know

  • A draft or submitted request can be withdrawn.
  • A deferred request can return to draft.