Go-live readiness
The paper the steering group reads before it authorises go-live. It scores the readiness criteria and ends in one decision.
This page applies to the Implement solution stage.
IDK templates: IDK-21
Page in the app: /p/{projectId}/go-live
The go-live decision
There is one readiness review for each cutover plan.
- Score criteria. Mark each criterion met or not met.
- Open conditions. Each gap becomes an issue.
- Decision. Go, go with conditions, or no-go.
- Gate decision. The review never closes the gate. Ask for the gate decision on its own page.
Project manager guide
A readiness paper that shows the steering group where you stand, including what is still open.
- Score the criteria.
- Do now: Open each criterion. Read the register verdict. Where no register exists, record the status and the reason.
- Why: Registers give the facts. People add the rest.
- The app checks: Each criterion is read from the registers it names. A module that cannot be read makes its criteria unknown.
- Next: Turn gaps into conditions.
- Create the conditions.
- Do now: For each gap add a condition with an owner, a due date and a person who verifies it.
- Why: A gap without an owner is forgotten after go-live.
- The app checks: Conditions are issues linked to the review.
- Next: Ask for the decision.
- Ask for the decision.
- Do now: Add a note for the decision makers and request the decision.
- Why: Go, go with conditions and no-go lead to different work.
- The app checks: The supplier project manager recommends, the executive sponsor decides and the steering group chair closes. The review does not change the gate.
- Next: Request the gate decision on the Gates page.
How to do it
- Review the criteria. Owners provide evidence for each one.
- Close what you can. Turn gaps into issues with owners.
- Ask for the decision. The steering group decides.
Good to know
- The review evidences a gate item. The gate decision stays separate.